A project team is planning the next sprint review.

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.