A project sponsor provides a charter and appoints a project manager to implement a large...

A project sponsor provides a charter and appoints a project manager to implement a large project over 5 years. The sponsor then requests the project budget and

outcomes from the project manager.

What should the project manager do first?

A.

Review the provided charter, identifying and engaging stakeholders.

B.

Review timelines based on the sponsor ' s provided charter and determine outcomes.

C.

Discuss and agree on a budget and plan with the project sponsor.

D.

Hire experts to decide on budget, develop the project management pian, and determine outcomes.