A project scope was developed with numerous assumptions.

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"