A project schedule risk has turned into an issue.

A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?

A.

Update the risk management plan and send it to the project team.

B.

Update the schedule baseline to the new project time line.

C.

Escalate the issue to senior leadership for resolution.

D.

Work with relevant stakeholders to determine possible solutions.