A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer to

their team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimize

delays.

C.

Request that the receiving manager issue a change request to prolong the project by

two weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"