A project manager who Is new to an organization is given data that include information...

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

A.

Regression analysis

B.

Stakeholder analysis

C.

Qualitative risk analysis

D.

Decision tree analysis