A project manager submits several requests to purchase required hardware andknows from previous experience that...

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?

A.

Ask the legal team to review the RFP.

B.

Ask the project team to submit the RFP.

C.

Request approval of the RFP from the project sponsor.

D.

Request approval of the RFP from management.