A project manager recently took over an ongoing project.

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

A.

Undefined change control process

B.

Unidentified project risks

C.

Improper work breakdown structure (WBS)

D.

Incomplete requirements