PMI PMP Question Answer
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?