A project manager of an infrastructure development project receives multiple issues from the customer validation...

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date. What should the project manager do to manage such a situation for upcoming phases?

A.

Revise the project schedule to accommodate fixing discovered issues.

B.

Ensure customer validation occurs more frequently during the life cycle of the project.

C.

Review the customer validation team's test plan early in the life cycle.

D.

Ask the project team to increase unit testing of the deliverables.