A project manager meets with the development team to estimate the time required to complete...

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

A.

Planning poker

B.

Parametric estimating

C.

Three-point estimating

D.

Analogous estimating