A project manager is reviewing the team's Kanban board for an iteration with 16 tasks...

A project manager is reviewing the team's Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.

Will the project manager meet this objective?

A.

Yes, it will take 4 working days to complete these tasks based on the estimate.

B.

No, it will take 6 days to complete all these tasks based on the estimate.

C.

No, it will take 7 days to complete all these tasks based on the estimate.

D.

Yes, it will take 5 working days to complete these tasks based on the estimate.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"