A project manager is leading the construction of a branch office building for a national...

A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?

A.

Perform contract, financial, and administrative tasks.

B.

Finalize the in-progress administrative tasks.

C.

Evaluate contract and administrative tasks.

D.

Execute financial and administrative tasks.