A project manager is leading an online learning system development project for a government body.

A project manager is leading an online learning system development project for a government body. The project team is working on a new feature that needs a very

stable video streaming platform. A stakeholder from marketing suggests using a platform that has been used in other marketing projects. Following the endorsement

of senior management, the team soon adopts this platform. Yet during development, the team finds that the platform cannot handle multilanguage subtitles, which are

critical to the online learning system.

What should the project manager have done to avoid this situation?

A.

Ensured identification and documentation of detailed requirements as well as acceptance criteria before selecting the solution.

B.

Arranged a meeting between the stakeholder and the team to make sure the recommended streaming platform met all requirements.

C.

Reviewed the process and made sure the technical staff was properly authorized to select the program that met all requirements.

D.

Asked the streaming platform provider to give a presentation to all stakeholders and the project team.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"