A project manager is leading a team using agile practices.

A project manager is leading a team using agile practices. During a sprint, a stakeholder approaches a team member with a request for a minor functional change.

What should the team member do?

A.

Report the change request to the project manager and seek their guidance.

B.

Accommodate the request immediately, as it has only a minor impact.

C.

Raise the request during the daily coordination meeting for team discussion.

D.

Redirect the request to the product owner to discuss and evaluate.