A project manager is leading a project that is kicking off next month.

A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.

What should the project manager do first to ensure each stakeholder has the information they need?

A.

Develop a communications management plan that reflects the needs of the stakeholder community.

B.

Engage with each stakeholder to determine their information needs related to the project.

C.

Create a responsible, accountable, consulted, and informed (RACI) chart based on the stakeholders and their communications needs.

D.

Determine the most appropriate mechanisms to leverage when communications are necessary.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"