A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.