PMI PMP Question Answer
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?