A project manager is confused when the operational results from previous iteration solutions have not...

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?

A.

Recommend a change in the project methodology or the approach.

B.

Develop and execute a stakeholder engagement strategy.

C.

Determine the criteria and measuring systems for objective success.

D.

Allocate more time for mentoring project team members.