A project manager is beginning a new project with very diverse team members.

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

A.

Create an environment where the agreement is reached by a majority vote.

B.

Create an environment where the agreement is reached through discussion.

C.

Establish recurring brainstorming sessions to discuss project issues.

D.

Allow team members to contribute ideas in a stream-of-consciousness mode.