A project manager is assigned to a new project.

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)