A project manager is appointed for the deployment of a new solution.

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"