A project manager has taken over an existing project According to the previous project manager,...

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)