A project manager has just taken over a project that is halfway through its schedule.

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"