A project manager has been managing a project for several months when an issue that...

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project ' s success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"