A project manager has been informed by a vendor that a shipment with supplies needed...

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan