A project manager has been assigned to a hybrid project that must receive approval from...

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

A.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert's availability within the organization on an as-needed basis.

C.

Develop the team member's capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"