A project manager has been assigned a low-priority project that includes new team members with...

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.