A project manager encounters a governance issue during the project execution phase.

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

A.

Clear responsible, accountable, consult, and inform (RACI) matrix

B.

Risk management and issues resolution plan

C.

Resource management and conflict resolution plan

D.

Clear project work breakdown structure (WBS) and timeline