A project manager assigned to an agile project realizes that after iteration demos, new user...

A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.

What should the project manager do?

A.

Review the minimum viable product (MVP) user stories and ensure all related stories are prioritized.

B.

Ask the team and product owner to reprioritize the user stories in the backlog for an updated iteration schedule.

C.

Ask the team to include the user stories as spikes in the next iteration to bring the project back on schedule.

D.

Add additional iterations to the schedule to accommodate for the work required on the stories.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"