A project management team received news that a competitor has released thelatest version of a...

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.