A project learn member is having difficulty delivering assigned tasks for a project that is...

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule