A project lead is working on a large-scale, high-profile hardware development project for a new...

A project lead is working on a large-scale, high-profile hardware development project for a new smartphone. The project sponsor has requested that a major priority feature almost fully

developed be considered optional. At the same time, a new priority feature that has never been discussed is being added.

Which two actions should the project lead take? (Choose 2)

A.

3 Ask the project sponsor to add funds to the project budget for the extra work.

B.

© Advise the product owner to deliver the original feature as a priority because it is almost completed.

C.

Ensure the product owner reflects the change in the product backlog.

D.

) Ask the project sponsor to review the contract to check if there are penalties for this change.

E.

Continue to monitor the budget and project timeline and escalate issues to management as needed.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"