A project is ending its fifth out of six iterations.

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

A.

Increase the team capacity to finish the project on time.

B.

Register an issue and escalate it to the project sponsor.

C.

Invite the stakeholders to discuss a new prioritization.

D.

Estimate the impact and consult with the product owner.