A project is 20% complete.

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?

A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.

B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.

C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.

D.

Consult the project sponsor to understand if the change must be processed for project execution.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"