A product owner is invited to a sprint review meeting.

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

A.

The product owner does not have visibility into what the team has done in the product increment.

B.

The product owner trusts the team and is marking the product as complete.

C.

The product owner has evaluated the product against the definition of done (DoD).

D.

The product owner will release the product to customers without showing them a demo.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"