A predictive project team come across a scenario where they need to use some agile...

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"