A leader from project B consistently reaches out to a team member in project A...

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

A.

Allow project B's leader to continue building relationships.

B.

Talk with project B's leader to discuss possible impacts to both projects.

C.

Tell project A's team member to ignore project B's leader.

D.

Ensure project A's team member can finish the work committed to project A.