New Year Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac75sure

A flagship project is sponsored by the CEO and has a critical go-live date.

A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.

What should the project manager do?

A.

Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).

B.

Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.

C.

Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.

D.

Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"