A defect is identified during user acceptance testing that could significantly impact the system's performance.

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"