A customer complains that the user stories released so far contain too much jargon and...

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.