A contractor has been making small changes to the engineering specifications without submitting change requests.

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

A.

Report the violation to the change control board (CCB) and seek comprehensive

approval for these modifications.

B.

Update the change management plan to define the level of control required for

these types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no action

because the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"