A company that is introducing a new product into the market by the end of...

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.