A company is transitioning from using a predictive approach to using an agile framework on...

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"