A CEO has requested that the project manager provide a budget estimate for a long-term...

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate