Your project team is executing the project plan and things are going well.

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

A.

Perform resource leveling for the project.

B.

Crash the project schedule.

C.

Fast track the project.

D.

Remove things from the project scope.

PMI-SP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-SP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"