You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?

A.

Spending is right on target.

B.

Costs are lower than planned.

C.

The project is behind schedule.

D.

Costs are higher than planned.