Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

You work as a project manager for BlueWell Inc.

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

A.

Contract Types

B.

Expert Judgment

C.

Procurement Negotiations

D.

Make-or-Buy Analysis

PMI-SP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-SP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"