You are working as a project manager for BlueWell Inc.

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

A.

Expert Judgment

B.

Decomposition

C.

Rolling Wave Planning

D.

Templates