You are the project manager of the NHQ project.

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

A.

$566,305

B.

$1,258,456

C.

-$54,044

D.

$503, 382